Mossy Oaks project on time, on budget

From staff reports

Work on the Mossy Oaks Stormwater Project remains on schedule and on budget, according to the latest update from Col. Neal Pugliese, USMC (Ret.), the Chairman of the Mossy Oaks Multijurisdictional Drainage Task Force.

Basin 1 

(vicinity of Duck Pond)

Lots of progress was made this week in Basin 1 in the vicinity of Jane Way, North Royal Oaks, West Royal Oaks, Battery Creek Road, and First Blvd., including the installation of drainpipes. These new pipes, set at the correct elevation, represent a large increase in capacity and capability.

The surrounding ditches have been graded and prepared for grass seed. Two 54-inch drainage systems were installed under Battery Creek Road where it intersects with the Duck Pond.

Between Broome and Rodgers along the Spanish Moss Trail, 1,000 feet of sewage pipe has been installed. That pipe is undergoing the first of two pressure tests to measure the pipe’s ability to process waste at full capacity.

Also, work began again on the West Royal Oaks ditch. Work has been slower than usual given the very damp nature of the ditch.

Finally, both BJWSA and Dominion Energy relocated their final service lines to accommodate the new drainage system.

Work will soon begin in earnest to pave Battery Creek Road. With good weather and warmer temperatures, we can expect the road to be closed for about four more weeks.

Crews have assembled 1,000 feet of high-pressure sewage line between Broome Lane and Rodgers. The transfer from the old service to the new service was scheduled for Tuesday, Dec. 16, from 10 p.m. to 6 a.m.

Finally, weather and soil conditions permitting, work along the ditch system between North Royal Oaks and West Royal Oaks will continue.

Basin 2 

(vicinity of Southside Park)

The project in this area is substantially complete with the contractor working on the final punch list items.

The drainage system along Battery Creek Road and Lawton Farms Road is functional and working as designed. Work on the Spanish Moss Trail in this basin is being done by another construction company and, as in Basin 1, about 1,400 feet of steel sheet pile are being driven into the Spanish Moss Trail between Riverside and Brotherhood.

To date, about 1,100 feet of steel reinforcing wall has been installed with about another 300 feet to go. Once the steel sheet wall is installe,d the tidal flap gates and drainpipes will be installed. At the current production rate, residents should expect another two weeks of steel sheet pile driving along the Spanish Moss Trail.

Stay informed

Those affected or interested in the Mossy Oaks Project should register with the “Notify Me” application found on the City of Beaufort website (https://www.cityofbeaufort.org/list.aspx) and subscribe to the Mossy Oaks Stormwater Project updates.

Previous Story

Public won’t be admitted for Wreaths Across America Beaufort

Next Story

Lowcountry Council of Governments seeks comment on hazard plan update

Latest from News

Lowcountry Lowdown

Future of USCB books sparks concerns By Lolita Huckaby BEAUFORT Banning of books in public school